Pteris Global Limited completed the project for Tocumen International Airport in the Republic of Panama in November 2006 in the design and building of its baggage handling system. The contract was awarded by the International Civil Aviation Organization (ICAO) on behalf of the Tocumen International Airport Authority (TIA). Pteris Global supplied the entire integrated system and its high-level control software for the airport. This was Pteris Global’s first project in the Latin American region and further augmented our track record of handling projects worldwide.

The Pteris Global project team stationed at Panama had the honor to welcome Singapore’s Foreign Affairs Minister Brigadier George Yeo and his team of delegates in 2006, and Deputy Prime Minister Dr. Jayakumar in 2007, on their state visits to Panama. They were given a first-hand tour on our Baggage Handling Systems in the Tocumen International Airport.

KEY FEATURES OF PROJECT

Project Completion Date : November 2006

Processing capacity : 4.4 million passenger annually

Pteris Global’s Scope of Work

  • 1.2km of Conveyor with walkway
  • 4 Arrival carousels
  • 6 Departure carousels
  • 1 Single Arm Plow
  • 1 Vertical Sortation Unit
  • 15 CAM pushers
  • Complete suite of High Level Control consisting of:
    – Sort Allocation Control (SAC)
    – Maintenance Diagnostic System (MDS)